| Audit: Brookhaven Capital Projects Costs Overruns ALBANY, N.Y. -- Cost overruns for Town of Brookhaven public works projects surpassed $2 million because town officials did not closely monitor the progress of the projects, according to an audit released in a press release Wednesday by state Comptroller Thomas P. DiNapoli. Click here for the pdf audit. Click here for the full press release. Spending for 43 of the town’s approximately 500 capital projects surpassed what the board authorized by a total of $2.2 million. This included the Mastic pool project which went over budget by $681,144 in December 2006. Money had to be diverted from other projects to cover the cost. Furthermore, between June 2002 and December 2006, the town paid a project manager for the pool project a total of $568,927 -- $508,927 more than the board had authorized. The audit, which covered the period January 2002 to December 2006, found that officials did not request or receive periodic reports that compared expenditures to their spending authorizations to ensure that money was available to pay for the work. Thirty-five project change orders totaling $372,870 did not receive town board approval prior to the work being done. In fact, change order work was often completed before the board even knew about the change orders and the additional costs. As a result, the board was unable to control spending or allocate additional appropriations when a project went over budget. DiNapoli recommended that town officials:
Town officials generally agreed with most of the Comptroller’s recommendations, but disagreed with the finding that officials kept inadequate accounting records. They also disagreed with the finding that there were no unauthorized expenditures for the Mastic pool project. The town’s full response is included in the audit. -- NYSSCPA.org News Staff Posted on 4/30/08 |